Posts

Starting to look finished

Image
 The upstairs bathroom is done except for some trim and finishing the vanity drawers.  Friend was here to get the water main hooked up in the crawlspace, set a couple toilets, and the water heater. I finished the wiring after and we have hot water and flushing toilets!  Jessica painted all the pocket doors and they are slid into the walls:)

busy busy busy

Image
Started tiling the upstairs bathroom floor.   Jessica painted the bottom of the T&G ceiling, looks amazing. Waterproofed the shower wall. Upstairs chinking started. Flooring delivered. First 2 mini splits installed and working.

drywall and paint done!

Image
 The drywall guys got the mud and texture finished last week. It was dry by Friday. We picked up primer and sprayed 12 gallons on Saturday. Then today we did another 15 gallons of paint. We also got the outdoor mini split unit mounted, and wired.  

Lots of progress, insulation & drywall!!

Image
 We've had a busy few weeks.   All inspection passed (plumbing, electric, mechanical, then rough framing) and we could insulate. Took a few days off to get a start on it. Mom and Dad came for a visit, and they helped for a few days, very thankful for that. Jessica and Mom worked on the beams, and Dad and I finished the ceiling insulation.   After insulation inspection passed, the drywall guys started. They are fast and really doing a great job. Hangers were done in about 4 long days, then tapers. Mudder/finisher should be starting in the next day or two, then paint!! Outside chinking is done!!!

Passed inspections

Image
 We pulled in our own AC cable from the meter base up to the house, that was fun! took some good pulls. Finished up the panel working and grounding, and passed our rough in.  We also passed the mechanical rough in(bath fans, dryer vent, wood stove ceiling box), and then passed rough framing. So now we are insulating, then drywall soon. Also 3 outside walls done chinking.

Busy week

Image
 Siding guys finished up so the dormers, gables and soffits are all done. Need paint. Greg came back out and dug a 100' trench, we ran a water line and 2" conduit for electric supply and 1" for Internet. We chinked the back wall , that's exciting. Jessica and I glued the conduit together. Inspection is tomorrow then backfill.   We also cut in a small window for the bathroom to let light in. And installed the ceiling support box for the wood stove.  The ceiling box for the wood stove is installed. Today I finished getting mule tape (flat pulling rope) into the power conduit. The doggy helped supervise. Installed the disconnect for the mini split outdoor unit, and added 3 chunks of conduit between the logs where the line sets will have to come through.

Getting sealed up

Image
 We have the inside and outside ready for chinking, likely to start this weekend. Siding guys are getting the soffits and gables and dormers finished with board n batten   Almost ready for electric, mechanical, and framing inspections. Laying out where the wood stove will go.