 Siding guys finished up so the dormers, gables and soffits are all done. Need paint.

Greg came back out and dug a 100' trench, we ran a water line and 2" conduit for electric supply and 1" for Internet.

We chinked the back wall , that's exciting.

Jessica and I glued the conduit together. Inspection is tomorrow then backfill.

 

We also cut in a small window for the bathroom to let light in. And installed the ceiling support box for the wood stove.





 The ceiling box for the wood stove is installed.


Today I finished getting mule tape (flat pulling rope) into the power conduit. The doggy helped supervise.

Installed the disconnect for the mini split outdoor unit, and added 3 chunks of conduit between the logs where the line sets will have to come through.