 course 8 completed. the middle and back girder logs are in and level. Next up is the center RPSL. We test fit it last weekend, but had to take it down to move the girder into place.   Also picked up some huge 1"x8" lag bolts for the girder brackets that or friend Jason is welding for us

course 8 almost done

Image
 Jessica working hard pealing a log. Layla supervising, watching for critters in the yard. One more log on the back wall and course 8 is done. Then setting second floor girder logs.

course 7 almost done

Image
 One more log, tomorrow after work, before the rain, and course 7 will be done. Then ready for second floor girder logs in course 8, and center rpsl